Show Observation

User: Ethan Rocklin

Created on: 2024-04-26

Observation Date 2024-04-25

Comment:
Soil finished the annually tilled micro-plot area in the LTER Main Site Treatment T7 Early Successional, Reps; (2, 4, 3, 1, 5, and 6) plots. Micro-plots were soil finished from North to South on the first pass, then from South to North on the second. Micro-plots were soil finished twice due to slightly higher soil moisture, leading to excessive soil clods. Headlands were soil finished going west to east on each north and south end of the plots.

Areas:
T7_micro-plots

Observation Type:
Soil Preparation Mechanical Weed Control

Activities:

Worker: Ethan Rocklin
Equipment: John Deere 7420a Tractor
Equipment: John Deere 960 10' field cultivator

Attachments:

Related Observations New observation Edit List Observations