Soil finished the annually tilled micro-plot area in the LTER Main Site Treatment T7 Early Successional, Reps; (2,4,3,1, 5 and 6) plots.
Micro-plots were soil finished from south to north in one pass.
Headlands were soil finished in two passes going west to east on each north and south end of the plots.
Areas:
T7_micro-plots
Observation Type:
Soil Preparation
Mechanical Weed Control
Activities:
Worker: Jarrod Rhoades
Equipment: John Deere 6420 Tractor
Equipment: John Deere 960 10' field cultivator