User: Brandon Mezo
Created on: 2014-05-30
Observation Date 2014-05-30
Comment:
Soil finished the LTER main site treatment T4, all replications as follows (6, 5, 3, 2, 1, 4) with a single pass with the JD7520 tractor and the JD726 soil finisher. Plots were soil finished on an angle to the NW-SE with 1 headland pass going E-W on both north and south side of each plot. All plots were finished to a 3-4” depth (soil finisher at ”B” setting), disc gang was set just at D. Speed was 7 mph depending on soil conditions. Reason for soil finishing a second time was to break up the soil clumps that were left from the previous soil finishing.
Areas:
T4
Observation Type: